This project is done in international cooperation between Banekonsortiet and Strukton Rail.
Activities
The project involves the renewal of circa 27,000 metres of track. The stations along the Svendborg-Odense line have double track; the rest of the railway line consists of single track.
The activities include:
-
27,000 metres track renewal with the P95 renewal train
-
22,000 metres of ballast renewal with the C750 ballast cleaner including ten MFS wagons for the ballast removal
-
27,000 metres of packing (with CSM and switch packing machine) including ballast plough + stabiliser
-
transport is done using a Strukton Rail locomotive