Strukton Rail has executed the Project Management over the entire project.
Description
The work of Strukton Rail contained the construction of crane gantries for the Automatic Stacking Cranes (ASC) on behalf of the container terminal, Terminal 3 West Extra. Strukton Rail also constructed crane gantries of a quay crane way and the ASC crane ways 275 up to 286, including accompanying activities.
The work involved
| Placing sleepers |
11,000 sleepers |
| Laying track on behalf of ASC crane ways |
8,000 metres |
| Laying track on behalf of quay crane ways |
650 metres |
| Placing concrete buffers |
48 buffers |