The Dutch utility company Enexis contracted Strukton Systems’ business unit Energy Solutions for the installation of ancillary equipment, earthing grid, cable connections, supporting structures and primary connections for their newly built substations in the Dutch towns of Klazienaveen and Luttelgeest. Both substations are needed to feed the sustainable electricity generated by horticultural businesses to the high-voltage grid.

Client:
Enexis
Location:
Luttelgeest & Klazienaveen
Activity:
Energy systems
Country:
The Netherlands
Enexis1
Enexis2
Enexis3
Enexis4

Supervision

Strukton Systems was also responsible for the installation supervision of all main
items installed at the substations, such as power transformers and mediumvoltage
switchgear.

The overall commissioning and testing of the substations was part of the scope of
supply as well.

Project summary

Project summary

  • Installation of ancillary systems
  • Installation of earthing grid and cable routes
  • Installation of all primary connections
  • Testing and commissioning of the entire plant